"Major project S106 at the Berlin site successfully completed (...) The third floor, the last construction phase of the Berlin building S106, has now been completed and taken over by the users of Synthetic Modalities and Life Science Technologies. Planning for the 6-story building, including two basement floors, began in 2015. The challenge was the conversion floor by floor while the laboratory was still in operation." (Georg Hamacher, Joerg Hartig, BayerNet / Bayer Intranet, Early 2024) Kommentare zu Georg Hamacher, Joerg Hartig, BayerNet, Early 2024: "Danke für eure Geduld und euren Einsatz, wenn wir mal wieder mit kurzfristigen Änderungen um die Ecke kamen" "Great wörk, Jörg!" Key data (2024) Laboratory type (mainly): Chemistry Gross floor area (GFA) ~12.000 m² Net floor area (NFA) ~10,000 m² Periodic table of elements 118 Elements
